Q. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
  • (A) 4 days
  • (B) 5 days
  • (C) 6 days
  • (D) 7 days
βœ… Correct Answer: (A) 4 days