Q. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

  • (A) 6 days
  • (B) 10 days
  • (C) 10.5 days
  • (D) 5 days