Q. A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

  • (A) 25/3 days
  • (B) 6 days
  • (C) 5 days
  • (D) 20/3 days
βœ… Correct Answer: (B) 6 days