Q. A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

  • (A) 12 days
  • (B) 15 days
  • (C) 16 days
  • (D) 10 days
โœ… Correct Answer: (B) 15 days