Q. X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • (A) 40/3 days
  • (B) 15 days
  • (C) 20 days
  • (D) 26 days
βœ… Correct Answer: (A) 40/3 days