πŸ“Š Math
Q. X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
  • (A) 40/3 days
  • (B) 15 days
  • (C) 20 days
  • (D) 26 days
βœ… Correct Answer: (A) 40/3 days

You must be Logged in to update hint/solution

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
404
Total Visits
πŸ“½οΈ
4 y ago
Published
πŸŽ–οΈ
Pradeep Sikarwar
Publisher
πŸ“ˆ
97%
Success Rate