Q. A and B can do a piece of work in 72 days, B and C can do it in 120 days and A and C can do it in 90 days. In how many days all three together can do the work ?

  • (A) 80 days
  • (B) 100 days
  • (C) 60 days
  • (D) 150 days
βœ… Correct Answer: (C) 60 days