Q. A and B together can complete a piece of work in 8 days, B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone takes to complete the work ?
  • (A) 15 days
  • (B) 18 days
  • (C) 16 days
  • (D) 20 days
βœ… Correct Answer: (C) 16 days