Q. A and B together complete a piece of work in T days. If A alone completes the work in T + 3 days and B alone completes the piece of work in T + 12 days, what is T ?

  • (A) 3 days
  • (B) 9 days
  • (C) 12 days
  • (D) None of these
βœ… Correct Answer: (D) None of these