Q. A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?
  • (A) 75
  • (B) 92
  • (C) 120
  • (D) 110
βœ… Correct Answer: (D) 110