Q. 20 persons completed 1/3rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?
  • (A) 20
  • (B) 12
  • (C) 18
  • (D) 40
βœ… Correct Answer: (A) 20

Explanation: Work done = 1/3
Remaining work = 2/3
So for double work in same days we need double number of people i.e. 40.

So, 20 men will be increased.

Explanation by: Madan
Work done = 1/3
Remaining work = 2/3
So for double work in same days we need double number of people i.e. 40.

So, 20 men will be increased.