Q. A and B can do a piece of work in 6 days and A alone can do it in 9 days. The time taken by B alone to do the same work is ?

  • (A) 18 days
  • (B) 15 days
  • (C) 12 days
  • (D) 7.5 days
βœ… Correct Answer: (A) 18 days

You must be Logged in to update hint/solution

πŸ“ Notes by Other Students/ Teachers


πŸ“Š Question Analytics

πŸ‘οΈ
417
Total Visits
πŸ“½οΈ
5 y ago
Published
πŸŽ–οΈ
Madan
Publisher
πŸ“ˆ
85%
Success Rate