Q. A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in ?
  • (A) 9.5 days
  • (B) 9 2/5 days
  • (C) 9 3/5 days
  • (D) 10 days
βœ… Correct Answer: (C) 9 3/5 days