Q. A and B together can complete a piece of work in 72 days, B and C together in 120 days and A and C together in 90 days. A, B and C together can complete the work in?
  • (A) 35 days
  • (B) 40 days
  • (C) 48 days
  • (D) 60 days
βœ… Correct Answer: (D) 60 days