Q. 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days ?

  • (A) 12
  • (B) 20
  • (C) 10
  • (D) 15
βœ… Correct Answer: (C) 10