Q. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be ?

  • (A) 12 days
  • (B) 10 days
  • (C) 9 days
  • (D) 8 days
βœ… Correct Answer: (B) 10 days