Q. A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs. 450. what will be the share of A in this amount of money ?
  • (A) Rs. 200
  • (B) Rs. 240
  • (C) Rs. 250
  • (D) Rs. 300
βœ… Correct Answer: (C) Rs. 250