Q. A certain number of men can do a piece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is ?

  • (A) 6
  • (B) 12
  • (C) 18
  • (D) 24
βœ… Correct Answer: (B) 12