πŸ“Š Math
Q. A certain number of men can do a piece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is ?
  • (A) 6
  • (B) 12
  • (C) 18
  • (D) 24
βœ… Correct Answer: (B) 12

You must be Logged in to update hint/solution

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
189
Total Visits
πŸ“½οΈ
12 mo ago
Published
πŸŽ–οΈ
Ritu Nagar
Publisher
πŸ“ˆ
83%
Success Rate