Q. 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is ?

  • (A) 2 : 1
  • (B) 3 : 1
  • (C) 1 : 3
  • (D) 5 : 4
βœ… Correct Answer: (A) 2 : 1