Q. 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • (A) 6
  • (B) 8
  • (C) 10
  • (D) 12
  • Correct Answer - Option(B)