A Admin • 37.39K Points Coach Math Bookmark Embed Report View In MB-Short Q. A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ? (A) 24 days (B) 18 days (C) 16 days (D) 20 days Correct Answer - Option(A) Views: 84 Filed under category Math Share