Q. A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

  • (A) 24 days
  • (B) 18 days
  • (C) 16 days
  • (D) 20 days
  • Correct Answer - Option(A)