R Ravi Shankar • 4.19K Points Extraordinary Math Bookmark Embed Report View In MB-Short Q. A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ? (A) 16 days (B) 24 days (C) 28 days (D) 29 days Correct Answer - Option(B) Views: 110 Filed under category Math Share