Q. If x can finish a job in 4 hours and y can finish the same job in 8 hours independently, then they together will finish the job in ?
  • (A) 140 minutes
  • (B) 160 minutes
  • (C) 120 minutes
  • (D) 150 minutes
βœ… Correct Answer: (B) 160 minutes