Q. 15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is ?

  • (A) 10
  • (B) 20
  • (C) 30
  • (D) 35
βœ… Correct Answer: (C) 30