πŸ“Š Math
Q. If 6 men can complete a work in 15 days, how many men are needed to do it in 10 days?
  • (A) 9
  • (B) 8
  • (C) 10
  • (D) 12
βœ… Correct Answer: (A) 9

Explanation: Men ∝ 1/time; 6×15 = M×10 → M = 9

Explanation by: Krishna Sharma
Men ∝ 1/time; 6×15 = M×10 → M = 9

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
15
Total Visits
πŸ“½οΈ
20 d ago
Published
πŸŽ–οΈ
Krishna Sharma
Publisher
πŸ“ˆ
95%
Success Rate