Q. If 4 workers complete a task in 10 days, how many days will 5 workers take to complete the same task?

  • (A) 5 days
  • (B) 6 days
  • (C) 7 days
  • (D) 8 days
βœ… Correct Answer: (D) 8 days
Explanation: Work ∝ 1/Workers → 4 × 10 = 40 man-days → 40/5 = 8 days.
Explanation by: Mr. Dubey
Work ∝ 1/Workers → 4 × 10 = 40 man-days → 40/5 = 8 days.