πŸ“Š Math
Q. If 12 men can complete a piece of work in 15 days, in how many days will 20 men complete the same work?
  • (A) 9 days
  • (B) 10 days
  • (C) 8 days
  • (D) 12 days
βœ… Correct Answer: (A) 9 days

Explanation: Work ∝ 1/men → 12 × 15 = 180 man-days → 180/20 = 9 days.

Explanation by: Mr. Dubey
Work ∝ 1/men → 12 × 15 = 180 man-days → 180/20 = 9 days.

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
24
Total Visits
πŸ“½οΈ
3 mo ago
Published
πŸŽ–οΈ
Mr. Dubey
Publisher
πŸ“ˆ
82%
Success Rate