Q. If 4 workers complete a job in 18 days, how many days will 6 workers take?

  • (A) 10 days
  • (B) 11 days
  • (C) 12 days
  • (D) 13 days
βœ… Correct Answer: (C) 12 days
Explanation: Work ∝ 1/men → 4 × 18 = 72 man-days → 72 / 6 = 12 days.
Explanation by: Mr. Dubey
Work ∝ 1/men → 4 × 18 = 72 man-days → 72 / 6 = 12 days.