Q. If 4 workers complete a job in 18 days, how many days will 6 workers take?
β
Correct Answer: (C)
12 days
Explanation: Work ∝ 1/men → 4 × 18 = 72 man-days → 72 / 6 = 12 days.
Explanation by: Mr. Dubey
Work ∝ 1/men → 4 × 18 = 72 man-days → 72 / 6 = 12 days.