Q. If 7 workers can complete a job in 12 days, how long will 14 workers take?
β
Correct Answer: (C)
6 days
Explanation: 7 × 12 = 84 man-days → 84/14 = 6 days.
Explanation by: Mr. Dubey
7 × 12 = 84 man-days → 84/14 = 6 days.