Q. If 6 men can complete a task in 12 days, how many days will 9 men take?

  • (A) 6
  • (B) 7
  • (C) 8
  • (D) 9
βœ… Correct Answer: (C) 8
Explanation: Work ∝ 1/workers → 6 × 12 = 72 man-days → 72/9 = 8 days.
Explanation by: Mr. Dubey
Work ∝ 1/workers → 6 × 12 = 72 man-days → 72/9 = 8 days.