Q. If 8 workers finish a task in 12 days, how long will 6 workers take?

  • (A) 12 days
  • (B) 14 days
  • (C) 16 days
  • (D) 18 days
βœ… Correct Answer: (C) 16 days
Explanation: Work ∝ 1/workers. (8 × 12) = (6 × x) → x = 16.
Explanation by: Ankit Singh
Work ∝ 1/workers. (8 × 12) = (6 × x) → x = 16.