Q. A and B together do a work in 12 days. A alone can do it in 20 days. In how many days can B alone do it?
  • (A) 25 days
  • (B) 28 days
  • (C) 30 days
  • (D) 32 days
βœ… Correct Answer: (C) 30 days

Explanation: Together = 1/12, A = 1/20 → B = 1/12 - 1/20 = 1/30.

Explanation by: Yami Thakur
Together = 1/12, A = 1/20 → B = 1/12 - 1/20 = 1/30.