Q. A can do a job in 40 days. B joins him and they finish it in 15 days. In how many days can B alone complete it?
  • (A) 20 days
  • (B) 24 days
  • (C) 30 days
  • (D) 40 days
βœ… Correct Answer: (B) 24 days

Explanation: Let B = x days. 1/40 + 1/x = 1/15 → x = 24 days.

Explanation by: Yami Thakur
Let B = x days. 1/40 + 1/x = 1/15 → x = 24 days.