Q. A and B together complete a work in 14 days. A alone can finish it in 21 days. In how many days can B alone do it?

  • (A) 30 days
  • (B) 36 days
  • (C) 42 days
  • (D) 49 days
βœ… Correct Answer: (C) 42 days
Explanation: 1/14 - 1/21 = 1/42.
Explanation by: Yami Thakur
1/14 - 1/21 = 1/42.