Q. A does 1/4 of a job in 9 days while B does 1/5 of the job in 10 days. Working together, how long will they take?
  • (A) 8 days
  • (B) 9 days
  • (C) 10 days
  • (D) 12 days
βœ… Correct Answer: (C) 10 days

Explanation: A = 1/36, B = 1/50 → together = 43/1800. Time = 1800/43 ≈ 10 days.

Explanation by: Ankit Singh
A = 1/36, B = 1/50 → together = 43/1800. Time = 1800/43 ≈ 10 days.