πŸ“Š Math
Q. A and B together do a work in 8 days. B and C do it in 10 days. C and A do it in 12 days. In how many days will A alone complete it?
  • (A) 14 days
  • (B) 18 days
  • (C) 20 days
  • (D) 24 days
βœ… Correct Answer: (D) 24 days

Explanation: Add all: 1/8 + 1/10 + 1/12 = 47/120. (A+B+C) = half = 47/240. Use A = (A+B+C)−(B+C).

Explanation by: Ankit Singh
Add all: 1/8 + 1/10 + 1/12 = 47/120. (A+B+C) = half = 47/240. Use A = (A+B+C)−(B+C).