Q. If 12 men can complete a work in 18 days, how many men needed to finish in 9 days?

  • (A) 18 men
  • (B) 24 men
  • (C) 30 men
  • (D) 36 men
βœ… Correct Answer: (B) 24 men
Explanation: Men ∝ 1/time → 12×18=24×9.
Explanation by: Ankit Singh
Men ∝ 1/time → 12×18=24×9.