Q. A does a work in 12 days. How much of the work does he complete in 7 days?

  • (A) 5/12
  • (B) 6/12
  • (C) 7/12
  • (D) 8/12
βœ… Correct Answer: (C) 7/12
Explanation: Work done = 7/12.
Explanation by: Kartik Sharma
Work done = 7/12.

πŸ“ Notes by Other Students/ Teachers


πŸ“Š Question Analytics

πŸ‘οΈ
82
Total Visits
πŸ“½οΈ
11 mo ago
Published
πŸŽ–οΈ
Kartik Sharma
Publisher
πŸ“ˆ
80%
Success Rate