Q. A completes 50% of a work in 8 days. What is the total time required to finish the entire work?
β
Correct Answer: (C)
16 days
Explanation: If half work = 8 days, full work = 16 days.
Explanation by: Kartik Sharma
If half work = 8 days, full work = 16 days.