Q. A and B can complete a work in 12 days. B alone can complete it in 18 days. A alone can complete it in?

  • (A) 24 days
  • (B) 30 days
  • (C) 36 days
  • (D) 20 days
βœ… Correct Answer: (C) 36 days
Explanation: 1/12 - 1/18 = 1/36.