Q. A can finish a work in 14 days and B in 21 days. Together they work for 6 days. What work remains?

  • (A) 1/7
  • (B) 2/7
  • (C) 3/7
  • (D) 4/7
βœ… Correct Answer: (B) 2/7
Explanation: 1/14 + 1/21 = 5/42. In 6 days = 30/42 = 5/7 done. Remaining = 2/7.