Q. A completes a work in 25 days. B is 25% more efficient than A. B will complete the work in?
  • (A) 18 days
  • (B) 20 days
  • (C) 22 days
  • (D) 24 days
βœ… Correct Answer: (B) 20 days

Explanation: Efficiency increases by 25%
-> time reduces by 20% -> 25 x 0.8 = 20 days.