Q. A can complete a work in 30 days. He works for 12 days and leaves. What fraction of the work is left?
β
Correct Answer: (B)
3/5
Explanation: Completed = 12/30 = 2/5. Remaining = 3/5.
Explanation by: Deepak Sahoo
Completed = 12/30 = 2/5. Remaining = 3/5.