Q. A can complete a work in 24 days. B can complete the same work in 16 days. If both work together for 8 days, what fraction of the work is completed?
β
Correct Answer: (B)
5/6
Explanation: Combined rate = 1/24 + 1/16 = 5/48. In 8 days, work completed = 40/48 = 5/6.
Explanation by: Deepak Sahoo
Combined rate = 1/24 + 1/16 = 5/48. In 8 days, work completed = 40/48 = 5/6.