Q. A can complete a work in 24 days. B can complete the same work in 16 days. If both work together for 8 days, what fraction of the work is completed?

  • (A) 2/3
  • (B) 5/6
  • (C) 3/4
  • (D) 7/8
βœ… Correct Answer: (B) 5/6
Explanation: Combined rate = 1/24 + 1/16 = 5/48. In 8 days, work completed = 40/48 = 5/6.
Explanation by: Deepak Sahoo
Combined rate = 1/24 + 1/16 = 5/48. In 8 days, work completed = 40/48 = 5/6.