Q. A can complete a work in 10 days and B in 15 days. After working together for 4 days, what fraction of the work remains?

  • (A) 1/3
  • (B) 2/5
  • (C) 7/15
  • (D) 8/15
βœ… Correct Answer: (A) 1/3
Explanation: Combined rate = 1/6. Completed in 4 days = 2/3. Remaining = 1/3.
Explanation by: Deepak Sahoo
Combined rate = 1/6. Completed in 4 days = 2/3. Remaining = 1/3.