Q. A can complete a work in 27 days. After working for 9 days, he leaves. What fraction of the work is completed?

  • (A) 1/4
  • (B) 1/3
  • (C) 2/3
  • (D) 3/4
βœ… Correct Answer: (B) 1/3
Explanation: Completed = 9/27 = 1/3.
Explanation by: Deepak Sahoo
Completed = 9/27 = 1/3.