Q. A completes a work in 9 days and B in 18 days. Together they complete the work in:
β
Correct Answer: (B)
6 days
Explanation: Combined rate = 1/9 + 1/18 = 1/6. Hence time = 6 days.
Explanation by: Deepak Sahoo
Combined rate = 1/9 + 1/18 = 1/6. Hence time = 6 days.