Q. A completes a work in 9 days and B in 18 days. Together they complete the work in:

  • (A) 5 days
  • (B) 6 days
  • (C) 7 days
  • (D) 8 days
βœ… Correct Answer: (B) 6 days
Explanation: Combined rate = 1/9 + 1/18 = 1/6. Hence time = 6 days.
Explanation by: Deepak Sahoo
Combined rate = 1/9 + 1/18 = 1/6. Hence time = 6 days.