Q. A completes a work in 24 days. After working for 8 days, what fraction of the work is left?

  • (A) 1/3
  • (B) 2/3
  • (C) 3/4
  • (D) 1/4
βœ… Correct Answer: (B) 2/3
Explanation: Completed = 8/24 = 1/3. Remaining = 2/3.
Explanation by: Deepak Sahoo
Completed = 8/24 = 1/3. Remaining = 2/3.