Q. A can complete 5/8 of a work in 20 days. How many days are required to complete the entire work?

  • (A) 24 days
  • (B) 28 days
  • (C) 30 days
  • (D) 32 days
βœ… Correct Answer: (D) 32 days
Explanation: Whole work = 20 × 8/5 = 32 days.
Explanation by: Deepak Sahoo
Whole work = 20 × 8/5 = 32 days.