Q. A can complete a work in 27 days and B in 54 days. Their combined efficiency is:

  • (A) 1/18
  • (B) 1/20
  • (C) 1/24
  • (D) 1/27
βœ… Correct Answer: (A) 1/18
Explanation: Combined rate = 1/27 + 1/54 = 1/18.
Explanation by: Deepak Sahoo
Combined rate = 1/27 + 1/54 = 1/18.