Q. A completes a work in 15 days. If his efficiency increases by 25%, the new time required is:
β
Correct Answer: (C)
12 days
Explanation: New time = 15 × 100/125 = 12 days.
Explanation by: Deepak Sahoo
New time = 15 × 100/125 = 12 days.